风力发电塔筒安装工艺控制要点 被引量:3

On controlling points for installation crafts for wind-power generation tower drum
下载PDF
导出
摘要 针对风力发电机组吊装高度高,体积大,质量重,且现场位于多风、高山位置的施工特点,主要从风力发电机组塔筒安装各阶段的控制要点、吊装方法的确定以及采取的控制措施方面进行了论述。从应用过程来看,塔筒安装过程中施工前准备、起吊、高强螺栓的紧固和塔筒各段的密封等过程均得到了有效控制。 According to the construction features for the wind power generators including high hoisting,big sizes,heavy weight,as well as windy and mountainous positions,the paper mainly indicates the controlling points of the stage,identification of hoisting methods and controlling measures of the installation of the wind power generators,and achieves effective control over the preparation,hoisting,tightening of high-strength bolting,and sealing of tower drum in sections.
作者 武晋辉 Wu Jinhui(Shanxi Industrial Equipment Installation Group Co.,Ltd.,Taiyuan 030008,China)
出处 《山西建筑》 2020年第9期81-82,共2页 Shanxi Architecture
关键词 风力发电 塔筒安装 高强螺栓 wind power generation installation of tower drum high-strength bolt
  • 相关文献

同被引文献26

引证文献3

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部