柱纵筋连接方式变更的结算过程剖析

Analysis on the settlement process of the change of column longitudinal bar connection mode
下载PDF
导出
摘要 通过结算新疆某项目中的某单位工程的变更签证单14HJ-U7-TJ-035,给出了计算变更签证的审核程序和处理流程,纠正了施工方错误的梁纵筋接头计算方法,明确了柱的定义,给出了柱和剪力墙边缘构件(端柱、有翼墙、转角墙)的区别,对今后土建结算中,梁、柱纵筋连接接头工程量的准确结算提供参考依据。 This paper presents the checking procedure and processing flow of the change visa form 14 HJ-U7-TJ-035 for the coalpreparation plant of the Xintian coal-to-natural gas project in Ili Kazakh Autonomous Prefecture,and corrects the incorrect calcula-tion method of the beam longitudinal bar joint,the definition of column is clarified,and the difference between column and shearwall edge members(end column,wing wall,corner wall) is given.
作者 张瑞娟 陈映棠 Zhang Ruijuan;Chen Yingtang(Shanxi Zhushi Architectural Design Co.,Ltd.,Taiyuan 030001,China;Shanxi Academy of Building Research Co.,Ltd.,Taiyuan 030001,China)
出处 《山西建筑》 2020年第9期151-153,共3页 Shanxi Architecture
关键词 电渣压力焊 机械连接 设计变更 工程造价 electro-slag pressure welding mechanical connection design change engineering cost
  • 相关文献

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部