期刊文献+

基于动态规划方法的变电站设备最优检修策略 被引量:2

Optimal Maintenance Strategy for Substation Equipment Based on Dynamic Programming Method
下载PDF
导出
摘要 基于历史规划和运行的可用数据,利用威布尔分布模型建立设备评估的可靠性函数。检修计划可能对不同设备有效使用寿命的最终状态产生影响。针对设备的最终状态,提出了最优检修方案,并对全寿命周期成本(LCC)和可靠性进行了比较。该算法采用动态规划方法,在满足可靠性和边界条件的前提下,给出了LCC最小值。分析结果表明了该方法的有效性,与遗传算法的结果相比其LCC值更小。 Based on the available data of historical planning and operation,the reliability function of equipment evaluation is established by means of Weibull distribution model.The maintenance scheduling may affect the final condition of the effective service life of different equipments.In allusion to the final condition of the equipment,the optimal maintenance scheme is put forward,the life cycle cost and the reliability are compared.This algorithm adopts dynamic programming method,and gives the LCC minimum value on the premise of satisfying the reliability and boundary condition.The analysis results show the effectiveness of this method,and its LCC value is less than that of genetic algorithm.
作者 张大宝 吴治勇 ZHANG Dabao;WU Zhiyong(State Grid Akesu Electric Power Supply Company,Akesu 843000,China)
出处 《国网技术学院学报》 2019年第6期13-16,共4页 Journal of State Grid Technology College
关键词 检修策略 可靠性 全寿命周期成本 动态规划 maintenance strategy reliability life cycle cost dynamic programming
  • 相关文献

参考文献3

二级参考文献33

共引文献44

同被引文献23

引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部