期刊文献+

山西某电厂黄土地层预应力高强混凝土管桩工程实践

Engineering Practice of PHC Pile in Loess Stratum of a Power Plant in Shanxi
下载PDF
导出
摘要 山西某新建2×350 MW低热值煤电厂主要建筑物地段出露地层为第四系上、中更新统黄土(粉土),厚度为40~60 m。其中(3-1)和(3-2)层粉土均匀分布于整个场地且力学性质较好,强度较高,是良好的桩端持力层。但该类地层含丰富的钙质、锰质结核,以往的勘察设计和施工单位大多采用钻孔灌注桩。基于其他工程的成功经验,我们选择采用预应力高强混凝土管桩进行工程试桩,分别采用长螺旋及大型机械洛阳铲进行引孔,通过高应变法检测进行对比检测,再通过静载荷试验最终验证,由此确定了合理的引孔直径和深度,成功总结出一套适合本工程地层的沉桩工艺。与原设计采用直径800 mm钻孔灌注桩方案相比,节省了一半的工程造价。本次实践证明了预应力高强度混凝土桩在黄土地层应用的可行性及可观的经济价值。 The stratum exposed in the main construction area of a newly built 2×350 MW low calorific value coal power plant in Shanxi is quaternary(upper and middle pleistocene series) loess(silty soil), with a thickness of 40 to 60 m. Among it,(3-1) and(3-2) layers of silt are evenly distributed in the whole site and have good mechanical properties as well as high strength. It can be used as a good bearing layer of the main building. But this stratum is rich in calcium and manganese nodules, so most of the survey and design or construction companies used to recommend the use of cast-in-place piles. Based on the successful experience of other projects, we chose PHC pile as the engineering pile testing, using long spiral drill or large mechanical Luoyang shovel respectively to pre-bore the hole. A contrast detection is carried out based on high-strain dynamic testing and then the static load test is also used as final verification, the reasonable diameter and depth of the pre-bored hole are thus determined, and a set of pile sinking technology fit for the stratum of this project is summed up. Compared with the original design of cast-in-place pile with a diameter of 800 mm, half of the project cost is saved. This practice proves the feasibility and considerable economic value of the application of PHC piles in the loess layer.
作者 严文根 方军 刘晓东 YAN Wengen;FANG Jun;LIU Xiaodong(China Sinogy Electric Group Co.,Ltd.,Shanghai,200065,China)
出处 《山西电力》 2020年第2期69-72,共4页 Shanxi Electric Power
关键词 黄土地层 预应力高强混凝土管桩 工程试桩 引孔 高应变法检测 loess stratum PHC pile engineering pile testing pre-bored hole high-strain testing
  • 相关文献

参考文献4

二级参考文献12

  • 1JGJ94-2008建筑桩基技术规范[S].北京:中国建筑工业出版社,2008.
  • 2何雄.地基基础工程检测[M].郑州:黄河水利出版社,2006.
  • 3《建筑施工手册》编写组.建筑施工手册[M].第4版.北京:中国建筑工业出版社,2004.
  • 4侯玉宾,吴继敏.桩基检测[M].南京:河海大学出版社,1998.
  • 5JGJ106-2003.建筑基桩检测技术规范[S].[S].,..
  • 6GB50025-2004湿陷性黄土地区建筑规范[S].北京:中国建筑工业出版社,2004.
  • 7JGJ 94-2008,建筑桩基技术规范[S].
  • 8ISBN978-7-112.08828-7,工程地质手册[M].北京:中国建筑工业出版社.2007.
  • 9JCJ106-97,基桩高应变动力检测规程[S].
  • 10邵晶晶.PHC管桩在太原地区的工程实践[J].山西建筑,2008,34(16):121-122. 被引量:1

共引文献6

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部