结合浙江文泰高速公路南浦溪特大桥钢管拱混凝土泵送顶升施工实际情况,介绍拱桥钢管混凝土配合比设计、顶升工艺设计、施工情况及紧急情况处理等经验,为同类工程提供借鉴。
Based on the actual construction situation of pumping and jacking of concrete filled steel tube at Nanpuxi Bridge of Wentai expressway in Zhejiang,this paper introduces the experience of mixing ratio design,jacking process design,construction and emergency treatment of concrete filled steel tube for arch bridge,which provides a reference for similar projects.
作者
杨忠波
Yang Zhongbo(China Railway ERJU 5th Engineering Co.,Ltd.,Chengdu Sichuan 610091,China)Abstract:Based on the actual construction situation of pumping and jacking of concrete filled steel tube at Nanpuxi)
出处
《城市建筑》
2020年第5期170-172,194,共4页
Urbanism and Architecture
关键词
钢管拱
混凝土
泵送顶升
steel tube arch
concrete
pumping and jacking