基于PSASP和EMTPE仿真软件,分析750 kV变电站A-变电站B输电线路发生单相永久接地后两侧开关重合闸时间不一致导致的短路电流直流分量问题,提出了解决方案。
By means of PSASP and EMTPE software,the DC component of the short-circuit current result by the disaccord reclosing timing of the switchs at the both sides of the line B after single phase permanent grounding of the line B in the 750 kv substation A is simulated and analyzed,and solutions are also put forward in this paper.
作者
傅国斌
陈卉
卢国强
王学斌
肖明
张舒捷
丁玉杰
赵东宁
FU Guobin;CHEN Hui;LU Guoqiang;WANG Xuebin;XIAO Ming;ZHANG Shujie;DING Yujie;ZHAO Dongning
出处
《青海电力》
2020年第1期58-61,共4页
Qinghai Electric Power
关键词
短路电流
直流分量
强弱系统
重合闸
short-circuit current
DC component
strong and weak system
reclosing