摘要
本文介绍排污水管分段加工、气囊滚动下水、海上拖航、现场注水沉放等环节的施工工艺,并就工艺实施过程中的船机配置情况和安全应急事项进行详细描述。由于管道拖运过程受风浪影响大,航行距离长,在穿越部分港池与航道时,应选择进出港船舶较少,无风无浪的天气时段进行出运。本文为外海类似钢制排污管道工程的施工具有指导意义。
This article introduces the construction process of the sewage pipe segment processing,airbag rolling and launching,sea towing,and on-site water injection and sinking.It also describes in detail the ship configuration and safety emergency issues during the process implementation.Because the pipeline hauling process is greatly affected by wind and waves,and the navigation distance is long,when crossing some harbors and waterways,it should be selected during the weather period when there are fewer ships entering and leaving the port and no wind and no waves.This article is of guiding significance for the construction of similar steel sewage pipelines in the open sea.
作者
管金海
付海兴
GUAN Jinhai;FU Haixing(China Communications First Aviation Bureau Second Engineering Co.,Ltd.,Qingdao Shandong 266000)
出处
《智能建筑与工程机械》
2019年第4期9-11,共3页
Intelligent Building and Construction Machinery
关键词
排污管道
浮拖
沉放
海上
sewage pipe
floating trailer
sinking
offshore