摘要
目前,我国正处在新一轮铁路大建设时期,铁路枢纽、编组站等规模不断扩大。与此同时,新建铁路线路不断引入枢纽、编组站,从而引起既有站场的改扩建,这促使既有大型站场逐渐趋于复杂化。本文针对大型复杂站场、结合工程设计实例对信号设计中遇到的特殊电码化及机车信号问题进行分析并提出解决方案。
At present,China is in the period of a new round of railway construction,and the scale of railway hub and marshalling station is expanding,at the same time,the new railway lines are constantly introduced into hubs and marshalling stations,which leads to the reconstruction and expansion of existing stations and yards,which makes the existing large stations and yards gradually become more complex.Aiming at large and complex stations,combined with engineering design examples,the special coding and locomotive signal problems encountered in signal design are analyzed and solutions are proposed.
作者
沙世伟
SHA Shiwei(China Railway First Survey and Design Institute Group Co.,Ltd.,Xi'an Shaanxi 710043)
出处
《智能建筑与工程机械》
2019年第4期123-126,共4页
Intelligent Building and Construction Machinery
关键词
大型站场
电码化
机车信号
解决方案
large station yard
coded code
locomotive signal
solution