期刊文献+

水布垭面板堆石坝运行初期水上部分面板脱空检测与分析 被引量:4

Detection and Analysis of Face Slab Void above Water in Early Operation Stage of Shuibuya Concrete Face Rockfill Dam
下载PDF
导出
摘要 水布垭面板堆石坝的面板脱空检测主要采用地质雷达普查和缺陷部位加密详查,声波垂直反射法对已确定缺陷的部位进行复查,这两种方法从不同角度反映面板脱空的状态,相互验证,提高了面板脱空检测成果的准确性,取得了良好的检测效果[1]。 In Shuibuya Hydropower Station,geological radar is adopted to generally examine the face slab void of the concrete face rockfill dam and densely investigate the possible void locations.Acoustic vertical reflection method is adopted to re-check the identified void locations.These two methods can reflect the void status of the face slab from different angles and the findings can be verified mutually,which improves the detection accuracy of the face slab void and achieves satisfactory performance.
作者 皮军华 杨威 李婧 PI Junhua;YANG Wei;LI Jing(Hubei Qingjiang Hydroelectric Development Co., Ltd., Yichang 443501, China;Powerchina Chengdu Engineering Co., Ltd., Chengdu 610072, China)
出处 《水电与新能源》 2020年第3期67-73,共7页 Hydropower and New Energy
关键词 面板堆石坝 脱空检测 地质雷达 声波垂直反射 concrete face rockfill dam void detection geological radar acoustic vertical reflection method
  • 相关文献

参考文献2

二级参考文献10

共引文献4

同被引文献42

引证文献4

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部