摘要
某水库工程大坝填筑料的运距在招标文件、投标文件中主次堆区填筑料运输距离描述不同。争议的焦点为结算依据不同,运输距离变化增加投资差异较大。通过分析按签订的合同文件作为结算依据。工程项目在合同签订事关实质性内容的协议时,承发包双方当事人都一定要谨慎评估。在合同订立过程中,无论是发包人还是承包人,都应该将正式合同与招投标过程文件作为一个整体看待,一定要仔细检查、分析、预测每一个细节可能对结算造成的影响。
The transportation distance of the dam filling materials of a reservoir project is described differently in the bidding documents and tender documents.The focus of the dispute is that the settlement basis is different,and the increase of investment due to the change of transportation distance is quite different.According to the analysis,the signed contract documents are taken as the settlement basis.When signing an contract concerning the substantive content of a project,both parties of the employer and the contractor must take careful evaluation.In the process of signing the contract,both the employer and the contractor should take the formal contract and bidding documents as a whole,and must carefully check,analyze and predict the impact of each detail on the settlement.
作者
李学明
张智涌
李桢
LI Xueming;ZHANG Zhiyong;LI Zhen(Sichuan Water Conservancy vocational College, Dujiangyan, Sichuan, 611830)
出处
《四川水力发电》
2020年第2期139-142,共4页
Sichuan Hydropower
关键词
结算依据
运距变化
合同解释
结算
settlement basis
change in distance
contract interpretation
settlement