装配式建筑工期效益影响因素分析及应对策略 被引量:13

Analysis on Influencing Factors of Construction Period Benefit of Prefabricated Buildings and Corresponding Strategies
下载PDF
导出
摘要 为提高装配式建筑的工期效益,分析实际工作中装配式建筑工期效益的主要影响因素:预制构件供货不及时、预制构件质量缺陷、管理效率低下等,运用AHP法对各因素的相对影响程度进行测算,发现管理问题是造成装配式建筑工期拖延的最主要原因。基于对各因素相对影响程度的测算结果及相关分析提出提高装配式建筑工期效益的合理化建议。 In order to improve the benefit of construction period of prefabricated buildings,the paper analyzes the main reasons for the delay of construction period of prefabricated buildings in practical work,including delayed delivery of prefabricated components,quality defects of prefabricated components and low management efficiency.Calculates the relative influence degree of various factors based on AHP method,finds that the management problem is the most important reason for the construction delay of prefabricated buildings.Based on the calculation results,puts forward reasonable suggestions to improve the construction period benefit of prefabricated buildings.
作者 李锦华 李雪强 周博 马辉 LI Jinhua;LI Xueqiang;ZHOU Bo;MA Hui(College of Economics and Management,Tianjin Chengjian Univeisity,Tianjin 300384,China)
出处 《建筑经济》 北大核心 2020年第4期64-69,共6页 Construction Economy
基金 天津市高等学校创新团队“建筑工业化与绿色发展”(TD13-5006)。
关键词 装配式建筑 工期 影响因素 应对策略 prefabricated building time limit for a project influencing factor strategies
  • 相关文献

参考文献6

二级参考文献30

  • 1熊鹰,匡亚萍.基于蚁群算法的施工项目工期-成本优化[J].系统工程理论与实践,2007,27(3):105-111. 被引量:29
  • 2清华大学《运筹学》教研组编.运筹学,清华大学出版社,1985.
  • 3麦圭根,李国津.管理经济学应用、战略与策略.北京:机械工业出版社,2000.
  • 4Daisy X M,Zheng S,Thomas N G,Mohan M.Kumaraswamy.Applying a genetic algorithm-based multiobjective approach for time-cost optimization[J].Journal of Construction Engineering and Management,2004,130(2):168-176.
  • 5Feng C W,Liu L,Burns S A.Using genetic algorithms to solve construction time-cost trade-off problems[J].Journal of Computing in Civil Engineering,1997,11(3):184-189.
  • 6Dorigo M,Gambardella L M.Ant colonies for travelling salesman problem[J].BioSystems,1997,43:73-81.
  • 7Zheng D,Ng S T,Kumaraswamy M.Applying a genetic algorithm-based multiobjective approach for time-cost optimization[J].Journal of Construction Engineering and Management,2004,130(2):168-176.
  • 8Zadeh L A.Fuzzy sets[J].Inf Control,1965,8:338-353.
  • 9KENZO K, NOBUYUKI N. Efficient Monte Carlo sim- ulation method of GERT - type network for project management [ J ]. Computers & Industrial Engineering, 2002,42(2 -4) :521 -531.
  • 10LUIS F A, DAVID B A, ANGELIQUE S H, et al. Risk planning and management for the panama canal expansion program [ J ]. Journal of Construction Engi- neering and Management ,2011,137 (10) : 111 - 113.

共引文献46

同被引文献114

引证文献13

二级引证文献61

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部