摘要
在大型桥梁施工中,大体积混凝土容易产生裂缝,将对工程质量产生重大安全隐患。论文全面总结了太阳冲大桥大体积混凝土施工中的温控计算、冷却水管布置和温度监控措施,对类似工程施工有一定的参考作用。
In the construction of large-scale bridge,the mass concrete is easy to produce cracks,which will cause major safety risks to the project.This paper comprehensively summarizes the temperature control calculation,cooling water pipe layout and temperature monitoring measures in the mass concrete construction of Taiyangchong Bridge,which has a certain reference role for similar project construction.
作者
黎泽俊
LI Ze-jun(China Railway No.5 Engineering Group Co.,Ltd.,Changsha 410000,China)
出处
《中小企业管理与科技》
2020年第5期162-163,共2页
Management & Technology of SME
关键词
铁路桥墩
大体积混凝土
温控技术
冷却水管
railway pier
mass concrete
temperature control technology
cooling water pipe