不停航条件下机场Ⅱ类仪表着陆运行项目箱型通道施工组织

The Construction Organization of the Airport TypeⅡInstrument Landing Operation Project Box Channel under Non-stopping Conditions
下载PDF
导出
摘要 本文对重庆江北机场02L跑道仪表着陆系统Ⅱ类运行改造项目管理过程中遇到的空侧下穿通道深基坑开挖、不停航施工、飞行爬升限制面下混凝土浇筑等重难点问题进行了分析梳理,并给出了行之有效的技术方案,可作为类似工程不停航施工的参考。 This paper analyzes and combs the difficult problems of deep foundation pit excavation,non-suspension construction,and concrete pouring under the restricted plane of flight climbing under the condition of the second class operation and transformation management of 02L runway instrument landing system of Chongqing Jiangbei Airport,and gives the effective technical scheme,which can be used as reference for the construction of similar projects.
作者 胡奇 李志成 林俊臣 Hu qi;Li Zhicheng;Lin Junchen(China Huaxi Enterprise Co.,Ltd.,Shenzhen 518034 Guangdong China;Chongqing airport group expansion command,Chongqing 401120 China;Sichuan Changdao Engineering Co.,Ltd.,Chengdu 610081 Sichuan China)
出处 《中国民航飞行学院学报》 2020年第3期26-30,共5页 Journal of Civil Aviation Flight University of China
关键词 仪表着陆系统 箱形通道 不停航施工 技术方案 ILS Box channel Non-stopping construction Technical scheme