摘要
兰新线自动闭塞区间继电式逻辑检查改造工程已经接近尾声,目前该工程处于开通前的联锁倒接试验阶段。在阐述区间逻辑检查功能性试验的基础上,模拟列车场景试验进行了进一步分析,对现场继电式逻辑检查电路的故障处理有一定的参考作用。
The transformation of relay logic checking of automatic block sections of Lanzhou-Xinjiang Railway is coming to the end. At present, the project is in the stage of interlocking test. On the basis of explaining the functional tests of relay logic checking, the paper makes further analysis by simulating train operation scenarios. And it can be used as a reference for fault treatment of relay logic checking circuits.
作者
王江平
Wang Jiangping(Jiayuguan Signal&Telecommunication Division,China Railway Lanzhou Group Co.,Ltd.,Jiayuguan 735100,China)
出处
《铁路通信信号工程技术》
2020年第5期86-91,共6页
Railway Signalling & Communication Engineering
关键词
兰新线
逻辑检查
联锁倒接试验
Lanzhou-Xinjiang Railway
logical check
interlocking test