期刊文献+

LNG储罐高承台灌注桩“一体成型”施工关键技术研究 被引量:1

Study on key technology of “one-in-one” construction of high platform filling pile of LNG storage tank
下载PDF
导出
摘要 本文针对一体成型施工法的灌注桩与上接桩(短柱)衔接施工技术、保障灌注桩中心与上接桩中心重合施工技术以及上接桩模板支护和灌注施工技术三方面关键技术进行深入分析,力求为同类型工程提供可参考的理论与实践基础。 In this paper, the key construction technologies of the one-in-one forming construction method, such as the connection construction technology between the cast-in-place pile and the up-connected pile(short column), the superimposition construction technology between the center of the safeguard cast-in-place pile and the center of the upconnected pile, and the formwork support and grouting construction technology of the up-connected pile, are analyzed and studied in depth, in order to provide a reference for the same type of engineering.
出处 《中国建材科技》 2020年第2期118-118,71,共2页 China Building Materials Science & Technology
关键词 LNG储罐 一体成型 灌注桩 高承台 LNG storage tank one-piece forming cast-in-place pile high platform
  • 相关文献

参考文献1

同被引文献6

引证文献1

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部