预制节段梁预应力体系智能化成套施工技术 被引量:1

Intelligent Construction Technology of Prestressed System of Precast Segmental Beam
下载PDF
导出
摘要 预制装配式桥梁采用龙门吊、架桥机等设备进行T构悬臂拼装、边跨拼装、施工合龙段,体系转换形成整联拼装连续梁桥。而架设过程中的预应力体系施工成为预制拼装梁桥的重要施工环节,它既是梁体的一道锁链,更是梁体的一道筋骨。对比国内外因预应力张拉压浆不规范而出现的各种质量问题及质量事故,皆是因张拉操作、压浆材料的水灰比、压浆过程的压力、浆液的充盈饱满等问题。预应力体系智能化施工技术以节段预制拼装桥梁施工为载体,研究预制节段梁桥智能张拉压浆施工方法,通过对施工工艺的探索、试验,总结出一套适用于预制节段梁预应力智能张拉压浆的施工技术,通过该成套技术的应用,保证了预应力体系施工质量,提高施工效率,缩短施工工期。 The precast and assembled bridge adopts the equipment of Gantry Crane and bridge erecting machine to assemble the t-shaped cantilever,the side Span,the closure section and the system transformation to form a continuous beam bridge.The prestress system construction in the process of erection becomes an important construction link of precast and assembled beam bridge.It is not only a chain of the beam body,but also a skeleton of the beam body.Compared with the various quality problems and quality accidents caused by non-standard prestress tension and grouting at home and abroad,they are all caused by tension operation,water-cement ratio of grouting material,pressure of grouting process,filling and fullness of grouting liquid,etc.The intelligent construction technology of pre-stressed system is based on the construction of segmental precast and assembled bridge,and the construction method of intelligent tensioning and grouting for precast segmental bridge is studied,this paper sums up a set of construction technology of prestress intelligent tension and grouting for precast segmental beam,through the application of this set of technology,the construction quality of prestress system is ensured,the construction efficiency is improved and the construction period is shortened.
作者 张清超 王宝兵 ZHANG Qingchao;WANG Baobing(China Water Resources and Hydropower Eleventh Engineering Bureau Co.,Ltd.,Zhengzhou Henan 450001,China)
出处 《工程质量》 2020年第S01期32-34,40,共4页 Construction Quality
关键词 预制节段梁 预应力体系 张拉压浆 智能化 技术 precast segmental beam prestressed system tension grouting intellectualization technology
  • 相关文献

参考文献3

二级参考文献10

  • 1JTGTF50-2011,公路桥涵施工技术规范[S].
  • 2酒井英昭.信号处理[M].北京:科学出版社,2001..
  • 3Cheng C,Sansalone M. Determining the Minimum Crack Width that Can Be Detected Using the Impact-echo Method Part I : Experimental Study [ J]. Material and Structures, 1995 (28) :74- 82.
  • 4Dennis A, Sack, Larry Dolson. Advanced NDT methods for eval- uating concrete bridges and other structures [ J ]. NDT&E Inter- nation, 1995,28 ( 6 ) :349-357.
  • 501son Instruments Inc. System reference manual 2007 impact- echo Scanning [ M ]. Colorado: Olson Instruments Inc,2007.
  • 6陈湘林.桥梁工程预应力混凝土结构施工技术[Z],200810.
  • 7朱新实;刘效尧.预应力技术及材料设备[M]北京:人民交通出版社,2005.
  • 8王伟,水中和,王桂明,余睿.冲击回波法检测波纹管灌浆质量的研究及工程实践[J].混凝土,2010(5):134-137. 被引量:38
  • 9邹春江,陈征宙,董平,邢姝,缪世贤,韩非.箱梁中冲击回波主频影响因素研究及应用[J].振动与冲击,2010,29(7):126-131. 被引量:19
  • 10王远平,魏剑伟,等.计算机在预应力混凝土结构张拉中的应用[J].工程力学,2001,18(A02):400-404. 被引量:12

共引文献6

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部