摘要 为了有效评价具有一般工期与随机返工的耦合设计任务评审策略,基于相型分布和连续时间马尔可夫链构建了项目完工时间概率分布估算解析模型。分析了两种基于平方变异系数的一般分布近似方法,选择其中一种更高效的方法对任务常规工期和返工工期进行近似,将任务执行相位视为虚拟任务进行项目网络转换;利用连续时间马尔可夫链描述转换网络的执行状态转移过程,并利用相型分布计算项目完工时间概率分布。以一类典型模具设计项目为例进行计算实验,分析多种项目环境参数对评审策略表现的影响,并通过模具设计项目案例分析验证了模型和方法的有效性。 To effectively evaluate the reviewing strategies for coupled design tasks with general activity durations and random rework,an analytical model for estimating the probability distribution of project completion time was constructed based on the phase-type distribution and continuous-time Markov chain.After analyzing two general distribution approximation methods based on squared?coefficient of variation,a more efficient method was selected to approximate the normal and rework activity duration.The project network was transformed by regarding each phase as a virtual task and the state transitions of the transformed network were described by a continuous-time Markov chain.The probability distribution of project completion time was finally obtained based on the phase-type distribution.Computational experiments were carried out taking a typical mold design project as an example,in which the influence of the project environmental parameters on the performance of reviewing strategy was analyzed.The proposed model and method were also verified by case study of mold design project.
作者 王梦娜 王小明 陈庆新 毛宁 WANG Mengna;WANG Xiaoming;CHEN Qingxin;MAO Ning(Guangdong Provincial Key Laboratory of Computer Integrated Manufacturing,Guangdong University of Technology,Guangzhou 510006,China)
出处 《计算机集成制造系统》 EI CSCD 北大核心 2020年第5期1336-1344,共9页 Computer Integrated Manufacturing Systems
基金 国家自然科学基金资助项目(51505090,51775120,61573109)。
关键词 设计评审 耦合任务 随机返工 连续时间马尔可夫链 相型分布 模具设计 design reviewing coupled-tasks random rework continuous-time Markov chain phase-type distribution mold design
  • 相关文献

参考文献4

二级参考文献67

  • 1钟登华,刘奎建,杨晓刚.施工进度计划柔性网络仿真的不确定性研究[J].系统工程理论与实践,2005,25(2):107-112. 被引量:30
  • 2徐航,朱一凡,陈春良.战伤装甲装备修理工时仿真及其分布规律研究[J].系统仿真学报,2006,18(10):2945-2947. 被引量:9
  • 3褚春超,陈术山,郑丕谔.基于依赖结构矩阵的项目规划模型[J].计算机集成制造系统,2006,12(10):1591-1595. 被引量:16
  • 4杨青海,祁国宁,黄哲人,郑克勤.基于案例推理和事物特性表的零件工时估算方法[J].机械工程学报,2007,43(5):99-105. 被引量:54
  • 5BROWNING T R, RAMASESH R V. A survey of activity network-based process models for managing product development projects[J].Production and Operations Management, 2007,16(2) : 217-240.
  • 6CLARKSON P J, SIMONS C, ECKERT C. Predicting change propagation in complex design[J]. Journal of Mechanical Design, 2004,126 (5) : 788-797.
  • 7LEMMENS Y, GUENOV M, RUTKA A, et al. Methods to analyse the impact of changes in complex engineering systems [C]//Proceedings of the 7th AIAA Aviation Technology, Integration, and Operations Conference(ATIO). Reston, Va. , USA: American Institute of Aeronautics and Astronautics Inc. , 2007 : 1345-1359.
  • 8OUERTANI M Z. Supporting conflict management in collaborative design:an approach to assess engineering change impacts [J]. Computers in Industry,2008,59(9) :882-893.
  • 9XIAO Renhin, SI Shangwen. Research on the process model of product development with uncertainty based on activity overlapping[J]. Integrated Manufacturing Systems, 2003, 14 (7) :567-574.
  • 10BROWNING T R, EPPINGER S D. Modeling impacts of process architecture on cost and schedule risk in product development[J]. IEEE Transactions on Engineering Management,2002,49(4) :428-442.