商合杭高铁矮塔斜拉桥主梁有索区施工工序优化 被引量:5

Shangqiu-Hefei-Hangzhou High Speed Railway Optimization of Construction Procedures at Cable Area of Extradosed Cable-stayed Bridge Girder
下载PDF
导出
摘要 以商合杭高铁矮塔斜拉桥工程为背景,为加快桥梁施工进度,在保证结构安全及受力合理的前提下,对斜拉桥主梁有索区的斜拉索张拉和挂篮走行的施工顺序进行调整,将主梁挂篮模板施工与斜拉索挂索张拉同步进行。采用Midas/Civil通用软件,计算分析了2种工序的应力和变形,并进行施工工期分析比较。结果表明,优化后既保证了施工安全,又节省了主梁施工工期。 The paper takes the extradosed cable-stayed bridge project on Shangqiu-Hefei-Hangzhou High Speed Railway as the study object and strives to make adjustment to the construction procedures for the tensioning of the stay cable and the moving of the suspended scaffolding,so as to speed up bridge construction,ensure structural safety and achieve more reasonable force loading.As the operation of the scaffolding for the main girder and the tensioning of the stay cable are carried out simultaneously,the paper introduces the general software of Midas/Civil for the calculation of the stress and deformation occurred in the two procedures.The results show that the optimization not only ensures construction safety but also cuts the construction period of the girder.
作者 张光亮 孙立新 张建国 ZHANG Guangliang;SUN Lixin;ZHANG Jianguo(CCCC Third Harbor Engineering Co Ltd,Shanghai 200000,China;Beijing-Fuzhou Railway Passenger Dedicated Line Anhui Co Ltd,Hefei Anhui 230001,China)
出处 《中国铁路》 2020年第6期77-81,共5页 China Railway
关键词 商合杭高铁 矮塔斜拉桥 斜拉索 施工工序 工期 有限元分析 优化 Shangqiu-Hefei-Hangzhou High Speed Railway extradosed cable-stayed bridge stay cable construction procedure for stay cable construction period finite element analysis optimization
  • 相关文献

参考文献10

二级参考文献46

共引文献174

同被引文献30

引证文献5

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部