面粉厂总承包现场管理是一项复杂的系统工程,主要包括施工前准备、设备安装、电气安装、电气调试、设备空载调试、带料调试、项目验收和移交等内容,需要各方各专业人员的共同参与和协作。现场管理的水平直接关系到整个项目工程的质量。
The site management of general contract in flour mills is a complex system project,which mainly includes the preparation before construction,equipment installation,electrical installation,electrical commissioning,equipment no-load commissioning,material commissioning,project acceptance and turnkey,etc.,which requires the joint participation and cooperation of all professional persons.The level of site management is directly related to the quality of the whole project.
作者
冯强
梁万礼
王向东
Feng Qiang;Liang Wanli;Wang Xiangdong(Wuxi COFCO Engineering & Technology Co., Ltd. ,Wuxi 214035)
出处
《粮食与食品工业》
2020年第3期10-12,共3页
Cereal & Food Industry
关键词
面粉厂
总承包
现场管理
工程质量
flour mills
general contract
site management
project quality