摘要
某水电站地处西北高原寒冷地区,且位于高山峡谷之中,综合考虑坝址区地质地形条件、水文气象特征、水工枢纽建筑物特点、导流建筑物布置、主体工程施工等因素,采用隧洞导流、围堰一次截断河床的导流方式,可节约工程工期,提高发电经济效益和社会效益,同时可为大中型高山峡谷寒冷地区水利枢纽导流设计提供参考。
The hydropower station is located in the cold and gorge area of the Northwest Plateau.Taking into account the topographical and geological conditions of the dam site area,the hydrological characteristics of the river,the layout characteristics of the hydraulic structure,the layout conditions of the diversion buildings,the construction of the main works,the diversion mode of tunnel diversion and primary closure cofferdam can save the project period,improve the economic benefits of power generation and social results.At the same time,it can provide a reference for the diversion design of large and medium hydropower stations in cold and gorge area.
作者
贺智安
王永胜
雷丽萍
He Zhi’an;Wang Yongsheng;Lei Liping(PowerChina Northwest Engineering Corporation Limited,Xi’an 710065,China)
出处
《山西建筑》
2020年第13期149-150,共2页
Shanxi Architecture
关键词
导流方式
导流标准
导流程序
导流隧洞
上下游围堰
diversion mode
diversion standard
diversion procedure
diversion tunnel
upstream and downstream cofferdam