多种穿插施工在高层住宅中的应用 被引量:4

Application of Multiple Interleaved Construction in High-rise Residence
下载PDF
导出
摘要 高层住宅施工工期较长,劳动力需求较高,制约了高层住宅产业化的发展。为提高施工效率,采用穿插流水施工管理技术,明确施工全过程从下往上流水的施工工序组织要求,可缩短施工工期,降低对劳动力数量的需求,提高工程管理的精细化水平。以杭州某地块二标项目为例,通过应用穿插施工,节约工期128d,减少工人120人,并取得了明显的经济效益,为类似项目提供了一套成功的穿插提效管理经验。 The construction period of high-rise residents is long and the labor demand is high,which restricts the development of high-rise residence industrialization.To improve the construction efficiency,the interleaved flow construction management technology is adopted to clarify the construction process organization requirements of the whole construction process from bottom to top,which can shorten the construction period,reduce the demand for the number of labor force,and improve the refinement level of project management.Taking the second bid project of a plot in Hangzhou as an example,through the application of interleaved construction,the construction period is saved by 128 d,120 workers are reduced,and obviou Is economic benefits are obtained,which provides a set of successful management experience of interleaved efficiency improvement for relative projects.
作者 邹小锋 ZOU Xiaofeng(Shanghai Jiashu Construction Project Co.,Ltd.,Shanghai 201108,China)
出处 《建筑施工》 2020年第5期736-737,共2页 Building Construction
关键词 高层住宅 工期 穿插施工 流水施工 工序 high-rise residence construction period interleaved construction flow construction process
  • 相关文献

同被引文献22

引证文献4

二级引证文献9

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部