摘要
在文献分析法和专家访谈法确定初始影响因素的基础上,利用因子分析法明确可能对装配式建筑施工安全造成影响的因素,通过在AHP法获得各指标权重,结合模糊数学的专业知识全面评价装配式建筑的施工安全,并利用此模型论证具体项目的安全状况。
This paper determines the initial impact factors based on the method of literature analysis and expert interview,processing data with the factor analysis method.Then it sets up an evaluation index system and determines the index weight with the analytic hierarchy process(AHP).Finally,it evaluates the safety situation with fuzzy mathematics and uses this model to demonstrate the safety status of a concrete prefabricated project.
作者
王春霞
王君仪
WANG Chun-xia;WANG Jun-yi(Shenyang Jianzhu University,Shenyang,Liaoning,110168,China)
出处
《建材技术与应用》
2020年第3期39-43,共5页
Research and Application of Building Materials