摘要
水泵水轮发电机组盘车,目的是为了检查机组安装或检修质量情况,通过对机组盘车测量的数据进行计算分析及处理调整,使机组摆度值满足标准规定要求。该文以惠蓄电站水泵水轮发电机组盘车为例,介绍惠蓄电站采用的“四表四点”盘车摆度测量原理及数据计算处理方法,为类似电站的机组盘车工作提供参考。
The turning of pump turbine generator unit,its purpose is to check the installation or maintenance quality of the unit.By calculating,analyzing and adjusting the data of turning measurement of the unit,to make the unit swing value meet the requirements of relevant standards.This paper takes the turning gear of pump turbine generator unit of Huizhou Pumped Storage Power Station as an example,to introduces the principle and calculation method of the swing measurement for the four dial gauges and four points turning gear used in Huizhou Pumped Storage Power Station,which Provides reference for turning work of similar hydropower station.
作者
谈进昌
TAN Jinchang(Huizhou Energy Storage Power Co., Ltd, Huizhou 516100,China)
出处
《广东水利水电》
2020年第6期65-70,共6页
Guangdong Water Resources and Hydropower
关键词
机组轴线
盘车
摆度
“两表八点”法
“四表四点”法
shaft line
turning
swing
method of two dial gauges eight points
method of four dial gauges four points