功率工况异常重要性判定方法在核安全监管中的应用 被引量:2

Application of Significance Determination Process at Power Condition in Nuclear Safety Regulations
原文传递
导出
摘要 介绍了国家核安全局开发的功率工况下核电厂异常重要性判定方法(SDP)的基本原理及方法,并使用该SDP对国内某核电厂发生的汽动辅助给水泵(ASG004PO)不可用事件进行了重要度和敏感性分析,结果表明该汽动辅助给水泵的再循环流量试验周期偏长。本文针对此问题给出了优化建议是将ASG004PO再循环流量试验的周期优化为小于34 d。 This paper describes the basic principles and methods of the significance determination process(SDP) at power condition, which was developed by the National Nuclear Safety Administration, and was used to analyze the significance and sensitivity of the failure of the pneumatic auxiliary feed pump(ASG004PO) in nuclear power plants. The result has indicated that the period of the recirculation flow test for the steam-driven auxiliary feed pump was too long, and the optimization proposal for this issue is to optimize the cycle of ASG004PO recirculation flow test to less than 34 days.
作者 马国强 李娟 丁珊珊 张延云 刘成运 Ma Guoqiang;Li Juan;Ding Shanshan;Zhang Yanyun;Liu Chengyun(Nuclear and Radiation Safety Center,Ministry of Ecology and Environment,Beijing,100082,China;Eastern Office of the National Nuclear Safety Administration,Shanghai,200233,China)
出处 《核动力工程》 EI CAS CSCD 北大核心 2020年第3期183-187,共5页 Nuclear Power Engineering
关键词 核电厂异常重要性判定方法 风险指引型 辅助给水系统 风险重要度 SDP Risk-informed Auxiliary feed water pump Risk significance
  • 相关文献

参考文献4

二级参考文献7

共引文献10

同被引文献6

引证文献2

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部