摘要
在污水处理厂提升改造项目中,特别是老旧污水处理厂进行提标改造中,设备更新和安装是非常重要的,它关系到污水处理厂提标改造的各项指标是否达到标准。结合具体污水处理厂不停水施工实例,简要探讨污水处理厂不停水施工中设备安装过程,主要包括:更换微孔曝气系统、曝气系统倾斜度测量、金刚石绳锯切割开洞、安装拦截筛网、推流器安装等工序,希望能对类似工程起到帮助。
In the upgrading and reconstruction projects of sewage treatment plants,especially the upgrading of old sewage treatment plants,equipment renewal and installation are very important.It is related to whether the indicators of the sewage treatment upgraded meet the standards.In this article,the author briefly discusses the equipment installation process in the non-stop water construction of the sewage treatment plant,including:replacement of the microporous aeration system,inclination measurement of the aeration system,and diamond wire saw cutting and opening,installation of intercepting screens,installation of flow pushers and other processes,hoping to help similar projects.
作者
张豪
ZHANG Hao(Fourth Engineering Co.Ltd.,18th Bureau Group,China Railway Tianjin 3000350)
出处
《河北建筑工程学院学报》
CAS
2020年第1期85-90,共6页
Journal of Hebei Institute of Architecture and Civil Engineering
关键词
不停水施工
微孔曝气系统
倾斜度测量
拦截筛网安装
推流器安装
non-stop water construction
microporous aeration system
inclination measurement
interception screen installation
flow locator installation