严寒地区铁路箱梁冬期施工温控实例分析 被引量:4

THERMAL CONTROL APPROACHES FOR THE WINTER CONSTRUCTION OF THE RAILWAY-BEAM PREFABRICATED FACTORY IN COLD REGIONS
下载PDF
导出
摘要 针对严寒地区铁路梁场生产需求,提出了具体的冬期施工方案,确定了从原材料、混凝土拌合与运输、箱梁浇筑与养护、压浆封锚等全过程的温度控制措施,并给出了混凝土冬期施工质量管控措施。文中冬期施工所采取的温控措施,可为后续严寒或寒冷地区类似梁场的冬期生产提供参考借鉴。 In terms of the requirements of the railway-beam prefabricated factory,the winter construction strategy is deployed.The thermal control approaches are identified for the raw materials,mixture and transportation of the concrete,casting and curing of the box beam,and grouting anchor.Also,the general quality control techniques are discussed in detail.The thermal control approach presented in this case can benefits the similar winter construction engineering of the railway-beam prefabricated factory.
作者 刘伟权 LIU Weiquan(Headquarters of the Railway Engineering Construction in Jiamusi,Harbin Railway Bureau Group,Harbin 150006,China)
出处 《低温建筑技术》 2020年第5期147-149,共3页 Low Temperature Architecture Technology
关键词 严寒地区 铁路梁场 冬期施工 温度控制 cold regions railway-beam prefabricated factory winter construction thermal control
  • 相关文献

参考文献4

二级参考文献3

  • 1铁科技[2004]120号文,客运专线预应力混凝土预制梁暂行技术条件[S].
  • 2TZ213-2005,客运专线铁路桥梁工程施工技术指南[S].
  • 3李巧玲.混凝土冬期施工要点[J].山西建筑,2010,36(8):168-169. 被引量:4

共引文献8

同被引文献31

引证文献4

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部