底板抽放巷支护方案分析与比选

Analysis and comparison of supporting schemes for floor extraction roadway
下载PDF
导出
摘要 随着底板抽放巷机械化装备水平的不断提升,整体单进水平也在不断的提高,但随着单进的提升,另一问题逐渐凸显,即在锚杆支护密度及强度方面,因底板抽放巷用途单一,若为达到巷道支护效果而加大锚杆支护密度及强度的情况,不仅增加施工任务量,影响施工进度,也在一定程度上造成支护材料的浪费。以4204底板抽放巷(下)为工程背景,运用数值模拟软件进一步优化该巷锚杆间排距,在保证巷道支护强度满足要求的前提下,提高了单进水平,可为同类型地质条件下矿井提供参考。 With the continuous improvement of mechanized equipment level of floor extraction roadway,the overall level of single entry was also constantly improving,but with the improvement of single entry,another problem was gradually highlighted,that was,in terms of bolt support density and strength,because the purpose of floor extraction roadway was single,if the density and strength of bolt support were increased to achieve the effect of roadway supporting,not only the construction task will be increased,but also the construction will be affected.The progress of construction also caused the waste of supporting materials to a certain extent.Based on the engineering background of 4204 floor extraction roadway(lower),the numerical simulation software was used to further optimize the row spacing between the bolts of the roadway.On the premise of ensuring that the supporting strength of the roadway met the requirements,the single entry level was improved,which provided a reference value for the mine under the same type of geological conditions.
作者 张志伟 Zhang Zhiwei(Production Technology Department,Hebi Coal Industry Co.,Ltd.,Henan Energy and Chemical Industry Group,Hebi 458030,China)
出处 《能源与环保》 2020年第6期164-167,共4页 CHINA ENERGY AND ENVIRONMENTAL PROTECTION
关键词 底板抽放巷 数值模拟 支护方案 工业性试验 floor extraction roadway numerical simulation supporting scheme industrial test
  • 相关文献

参考文献6

二级参考文献33

共引文献297

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部