摘要
当下装配式建筑市场发展迅速,预制构件图纸深化的要求逐步提高。通过在某工程实例中做好PC图纸审图与优化工作,提前发现和解决了碰撞类和预留预埋类等设计问题,并提出了一些利于现场施工的优化措施,避免了在施工过程中出现大量变更及后期返工。从施工角度总结了装配式图纸中的常见问题,为施工单位做好PC图纸审图工作提供了参考。
Presently,the prefabricated construction market is developing rapidly,and the requirements for deepening the drawings of prefabricated components are gradually increasing.By doing a good job of drawing review and optimization of PC drawings in a project example,design problems such as collision type and reserved-embedded type were found and solved in advance and some optimization measures for site construction were put forward to avoid a large number of changes and subsequent redrawing in the construction process.From the construction point of view,this paper summarizes the common problems in the PC drawings,which provides a reference for the construction unit to improve the work of PC drawing review.
作者
翟建雷
邵志兵
叶文启
汤静
ZHAI Jianlei;SHAO Zhibing;YE Wenqi;TANG Jing(Zhongtian Construction Group Co.,Ltd.,Hangzhou,Zhejiang 310008,China;Yangzhou Architectural Design and Research Institute Co.,Ltd,Yangzhou,Jiangsu 225007,China)
出处
《建筑施工》
2020年第6期994-996,共3页
Building Construction