摘要
现浇梁拆除施工风险较高,对周边环境影响大,论文以独柱墩单箱双室连续梁桥拆除施工为例,简要介绍了现浇梁拆除的施工工艺和措施,可为类似工程提供借鉴和参考。
The demolition of cast-in-place beam has high risk and great impact on the surrounding environment.Taking the demolition construction of single box double chamber continuous beam bridge with single-column pier as an example,this paper briefly introduces the construction technology and measures of the demolition of cast-in-place beam,which can provide reference for similar projects.
作者
宗朝阳
陈鹏
田玉婷
ZONG Chao-yang;CHEN Peng;TIAN Yu-ting(China State Railway Investment Construction Group Co.Ltd.,Beijing 100032,China)
出处
《工程建设与设计》
2020年第12期176-177,共2页
Construction & Design for Engineering
关键词
连续梁
拆除
破碎
continuous beam
demolition
crushing