摘要
岷江龙溪口航电枢纽工程距离犍为县城较近,土石方开挖量、弃渣量相对较大,实施阶段结合枢纽布置、导流方式、场区地形地质条件、交通运输条件、料场及弃渣场分布,通过进一步优化施工总布置,为工程顺利建设创造了良好条件。目前,龙溪口航电枢纽工程建设正在有序推进,从现场情况反映,施工总布置紧凑合理。
Minjiang Longxikou Navigation Power Junction project is close to the Jianwei County,and the total volumes of the earth-rock excavation and waste are rather large.In the project implementation phase,the general construction layout is further optimized,including the junction layout,construction diversion scheme,topographical and geological conditions,traffic and transportation requirements,and the embankment and waste material yard arrangement.Actual construction of the project shows that the optimized construction layout is reasonable and compact,which provides a satisfactory condition for the smooth implementation of the project.
作者
李志伟
张毅驰
陈海坤
LI Zhiwei;ZHANG Yichi;CHENG Haikun(Powerchina Guiyang Engineering Co., Ltd., Guiyang 550081, China)
出处
《水电与新能源》
2020年第7期60-63,共4页
Hydropower and New Energy
关键词
岷江龙溪口航电枢纽
枢纽布置
施工导流
施工总布置
Minjiang Longxikou Navigation Power Junction
junction layout
construction diversion
general construction layout