针对地铁通常采用的"先站后隧"做法带来的影响车站施工安排问题,提出"先隧后站"施工工法,包括管棚法、托梁法、半盾构法、结合矿山法、扩径盾构法等。采用这些做法可缩短施工工期,减少盾构机周转次数,降低对场地的需求,技术经济效益良好。
To avoid the influence of commonly-used"station-first and tunnel-second"method on station construction arrangement,"tunnel-first and station-second"construction method was proposed,including tubular shed method,joist method,semi-shielding method,mining method and diameterexpanding shielding method,etc.It could shorten the construction period,reduce turnover of shield machine,weaken the requirements for construction site and realize favorable technical and economic benefits.
作者
吴飞
王斌
WU Fei;WANG Bin(Beijing Construction Engineering Group Co.,Ltd.,100055,Beijing,China)
出处
《建筑技术》
2020年第7期800-802,共3页
Architecture Technology