某框架-剪力墙结构楼板开洞的设计方法 被引量:1

Design Method of the Floor Openings in a Frame-shear Wall Structure Floor
下载PDF
导出
摘要 针对某裙房结构,因楼板的凹入和开洞过大而造成此处楼板连接薄弱,设计阶段需要考虑由此造成楼板削弱而带来的不利影响,对薄弱部位进行加强处理。本文基于对某实际工程结构的计算分析,提出了可供同类结构设计参考的改进措施和方法。 For a podium structure,the connection of the floor slab is weak due to the large concavity and opening of the floor slab.In the design,the adverse effects caused by the weakening of the floor slab should be considered,and the weak parts should be strengthened.In this paper,the calculation of an engineering structure is carried out,and on the basis of comparative analysis,the improvement and strengthening measures are proposed.The calculation results show that the seismic design indexes are met,which can be used as reference for the design of similar structures.
作者 庄莉 冷斌 ZHUANG Li;LENG Bin(Institute of Architecture Design&Planning Co.,Ltd of Nanjing Unviersity,Nanjing Jiangsu 2100093 China)
出处 《江苏建筑》 2020年第3期32-34,共3页 Jiangsu Construction
关键词 工程结构 楼板削弱 薄弱部位 抗震设计 楼板开洞 engineering structure floor weakening weak position seismic design floor opening
  • 相关文献

参考文献6

二级参考文献18

  • 1姜堃,王翠坤,肖从真,钱稼茹,刘军进,林祥.一幢特别不规则高层建筑结构模型的振动台试验研究[J].建筑科学,2005,21(1):19-25. 被引量:9
  • 2林春阳,童谷生.弹塑性时程分析法验算七层框架薄弱层[J].山西建筑,2005,31(18):51-52. 被引量:2
  • 3中国建筑科学研究院PKPMCAD工程部.高层建筑结构空间有限元分析软件(SATWE)用户手册及技术条件[M].北京:中国建筑工业出版社,2005.
  • 4GB50011-2010,建筑抗震设计规范[S].
  • 5GB50011-2010建筑抗震设计规范[S].北京:中国建筑工业出版社,2010.
  • 6GB50010--2010混凝土结构设计规范[S].
  • 7裴星洙,张立,任正权.高层建筑结构地震响应的时程分析法[M].北京:中国水利水电出版社,2005:1-2.
  • 8.GB50011-2001建筑抗震设计规范[S].北京:中国建筑工业出版社,2001..
  • 9戴国莹,王亚勇.房屋建筑抗震设计[M].北京:中国建筑工业出版社,2005.
  • 10JGJ3-2002高层建筑混凝土结构技术规程[S].北京:中国建筑工业出版社,2002.

共引文献16

同被引文献7

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部