本文以甘肃省平凉市庄浪县阳川镇L安置区项目为实例,分别对现浇式和装配式两种建造方式进行工程概算,用定量方法分析成本差异,并找出造成成本差异的原因。在此基础上,对装配式建筑在新农村建设领域应用进行可行性分析。
This paper takes Yangchuan(Zhuanglang County,Pingliang City,Gansu Province)L resettlement project as an example,makes engineering budgetary estimates for cast-in-place and prefabricated construction,analyzes the cost differences with quantitative methods and finds the reasons.On this basis,the feasibility analysis of the application of prefabricated buildings in the new rural construction field is carried out.
作者
牛童
NIU Tong(Tianjin Hexi District Housing and Construction Comprehensive Administrative Law Enforcement Detachment,Tianjin 300000,China)
出处
《价值工程》
2020年第23期15-16,共2页
Value Engineering
关键词
新农村建设
装配式建筑
现浇式建筑
成本分析
new rural construction
prefabricated buildings
cast-in-place buildings
cost analysis