兰新通道嘉峪关及嘉峪关南站扩能改造方案研究 被引量:5

Renovation Plan for Jiayuguan and Jiayuguan South Station of Lanzou-Urumqi Railway Corridor
下载PDF
导出
摘要 兰新通道嘉峪关铁路地区点线能力不协调,造成兰新线运输能力释放不足,兰新高速铁路能力富余较大,成为制约兰通道运输效率的主要问题。通过对兰新通道现状、嘉峪关站及嘉峪关南站的分析,提出兰新通道嘉峪关及嘉峪关南站扩能改造3个方案:方案I:嘉峪关站扩能改造,方案Ⅱ:嘉峪关南合场方案,Ⅲ:嘉峪关南并场。经综合比选,推荐采用方案Ⅲ,有效解决了嘉峪关站到发线能力不足及客、货列车交叉干扰问题,提高了兰新通道整体运输效率。 The unbalanced capacity between stations and the line in the Jiayuguan Railway Area of Lanzhou-Urumqi Railway Corridor leads to insufficient release of transportation capacity of Lanzhou-Urumqi Line and abundant capacity of Lanzhou-Urumqi High-Speed Railway,which has become the main factor restricting the transportation efficiency of Lanzhou-Urumqi Railway Corridor.Based on the analysis of the current situation of Lanzhou-Urumqi Railway Corridor,Jiayuguan Station and Jiayuguan South Station,three renovation plans of Jiayuguan and Jiayuguan South Station are proposed:Plan I:capacity expansion and renovation of Jiayuguan Station;Plan II:merging of yards at Jiayuguan Station;Plan III:Parallel yards at Jiayuguan South Station.After comprehensive comparison and selection,Plan III is recommended,which effectively solves the problems of insufficient capacity of arrival-departure track and interference between passenger and freight trains at Jiayuguan Station and improves the overall transportation efficiency of Lanzhou-Urumqi Railway Corridor.
作者 左波祥 ZUO Boxiang(Track and Transportation Department,China Railway First Survey and Design Institute Group Co.Ltd.,Xi’an 710043,Shaanxi,China)
出处 《铁道运输与经济》 北大核心 2020年第7期45-49,共5页 Railway Transport and Economy
基金 中国铁建股份有限公司科技研究开发计划课题(14-C53)。
关键词 兰新通道 嘉峪关站 嘉峪关南站 扩能改造 运输效率 方案比选 Lanzou-Urumqi Railway Corridor Jiayuguan Station Jiayuguan South Station Capacity Expansion and Renovation Transportation Efficiency Plan Comparison
  • 相关文献

参考文献5

二级参考文献25

  • 1朱颖,王国生.铁路设计理念的回顾和展望[J].铁道工程学报,2007,24(1):1-5. 被引量:15
  • 2王玉泽.铁路线路设计回顾与思考[J].铁道工程学报,2007,24(1):27-31. 被引量:23
  • 3赵清为.铁路工程技术手册-线路[K].北京:中国铁道出版社,1994.
  • 4中铁二院工程集团有限责任公司.改建铁路广通至大理线扩能改造工程预可研报告[R].成都:中铁二院工程集团有限责任公司,2007.
  • 5铁道部.铁路工程建设标准局部修订条文汇编[G].北京:中国铁道出版社,2009.
  • 6乔文贤,等.改建铁路皖赣线增建第二线工程预可行性研究[R].武汉:中铁第四勘察设计院集团有限公司,2008.
  • 7王海明,等.改建铁路石门至长沙线增建第二线工程预可行性研究[R].武汉:中铁第四勘察设计院集团有限公司,2008.
  • 8杨东,等.改建铁路赣龙铁路复线预可行性研究[R].武汉:中铁第四勘察设计院集团有限公司,2008.
  • 9郝瀛.铁路选线设计[M].北京:中国铁道出版社,1996..
  • 10TB10002.1-2005,铁路桥涵设计基本规范[S].

共引文献111

同被引文献50

引证文献5

二级引证文献4

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部