钢柱式整体爬升钢平台模架同步提升技术研究

Research on Synchronous Lifting Technology of Steel Column Type Integral Climbing Steel Platform Formwork
下载PDF
导出
摘要 多机位同步提升控制是钢柱式整体爬升钢平台模架关键技术之一。以南京金鹰T2塔楼核心筒竖向结构施工为例,从机位实测位移和顶升力数据出发,探寻影响同步性提升控制关键因素,提出进一步提升同步性控制水平的方法,为钢柱式整体爬升钢平台模架的安全使用和推广提供理论支撑。 Multi-machine synchronous lifting control is one of the key technologies of steel column type integral climbing steel platform formwork.Taking the core tube vertical structure construction of Nanjing Golden Eagle T2 tower as an example,starting from the measured displacement and lifting force data of the machine,this paper explores the key factors affecting the synchronous lifting control,and puts forward the method to further improve the synchronous control level,which provides theoretical support for the safe use and promotion of the steel column type integral climbing steel platform formwork.
作者 秦鹏飞 QIN Pengfei(Shanghai Construction Group Co.,Ltd.,Shanghai 200080,China;Shanghai Engineering Research Center of Mega Structure Construction Technology and Equipment,Shanghai 201114,China)
出处 《建筑施工》 2020年第7期1208-1211,共4页 Building Construction
基金 国家重点研发计划项目(2018YFC0705800) 上海市科委科研计划项目(18DZ2282800) 上海建工集团股份有限公司科研项目(17YJKF-03,18YJKF-04)
关键词 钢平台模架 液压缸 液压系统 同步性控制水平 steel platform formwork hydraulic cylinder hydraulic system synchronization control level