摘要 山东某炼厂新建一除盐水站,采用多介质过滤器+活性炭过滤器+反渗透装置+阳床+阴床+混床处理工艺,以实现出水水质满足锅炉补水和炼化装置用水的要求。运行过程中出现了反渗透装置污堵快、化学清洗频繁,以及混床再生周期短的问题。对现场工况进行分析,调整了药剂投加量和加药点位置,并用碱液对全部树脂罐中的树脂进行处理,有效延长了反渗透装置的化洗周期及混床的再生周期。 A Shandong refinery construct a new desalination station. The main process including multimedium filter+activated carbon filter+RO+cation exchanger+anion exchanger+mixed bed exchanger is involved to achieve the demand of boiler and refining device. The problem of RO device fouling fast and chemical cleaning frequently and regeneration cycle of mixed bed short raised in the process of reverse osmosis device. By analyzing on-site operating conditions,the dosage and dosing position were adjusted,and resin was treated with the alkali solution,which prolonged the cycle of RO CIP and resin regeneration.
作者 曹宏伟 程建峰 王治民 聂明 许跃 刘向朝 Cao Hongwei;Cheng Jianfeng;Wang Zhimin;Nie Ming;Xu Yue;Liu Xiangzhao(Tianjin Haihua Environmental Engineering Co.,Ltd.,Tianjin 300280,China;North China Petrochemical Branch,CNPC,Renqiu 062550,China;Tianjin Academy of Eco-Environmental Science,Tianjin 300191,China)
出处 《工业水处理》 CAS CSCD 北大核心 2020年第8期116-119,共4页 Industrial Water Treatment
关键词 除盐水站 反渗透 混床 desalination station reverse osmosis mixed-bed
  • 相关文献

参考文献3

二级参考文献8

  • 1朱兴宝.降低阴床出水含硅量的探讨.水处理技术,1985,(1):51-53.
  • 2朱兴宝.阴双层床树脂混层的研究.净水技术,1985,4(3):1-4.
  • 3朱兴宝.阴双层床中选择两种树脂最佳配比的计算方法.湖北电力技术,1984,(3):43-47.
  • 4施燮钧,王泉聚,肖作善.热力发电厂水处理[M].北京:中国电力出版社,1996.
  • 5陈沽,杨东方.锅炉水处理技术问答[M]北京:化学:工业出版社,2003.
  • 6李培元.火力发电厂水处理及水质控制[M].北京:中国电力出版社,2009.
  • 7刘晓,周菊华.电厂水处理及化学监督[M].北京:中国电力出版社,2012.
  • 8李欣,孟强,文功谦,朱兴宝.强碱阴树脂硅污染的复苏[J].净水技术,2010,29(2):67-70. 被引量:6