摘要
分析大口径顶管穿越段管道阴极保护存在的问题。结合工程实例,对大口径顶管穿越段管道和紧固件牺牲阳极阴极保护方案进行探讨。
The problems existing in the cathodic protection of large-diameter pipe jacking crossing section are analyzed.Combined with engineering examples,the sacrificial anode cathodic protection scheme of large-diameter pipe jacking crossing section and fasteners is discussed.
作者
俞翔
茅斌辉
祝俊宗
刘国
YU Xiang;MAO Binhui;ZHU Junzong;LIU Guo
出处
《煤气与热力》
2020年第8期37-39,J0044,共4页
Gas & Heat
关键词
顶管穿越
大口径管道
紧固件
牺牲阳极
阴极保护
强制电流
pipe jacking crossing
large-diameter pipe
fastener
sacrificial anode
cathodic protection
impressed current