摘要
文中介绍了运城市北赵引黄二期工程扩建的必要性和北赵引黄灌区的基本情况,对干渠建筑物渡槽改倒虹后进行了水力计算分析,同时通过施工条件、运行管理及工程投资进行综合比较,确定设计方案。
This paper introduces the necessity of the expansion of the second phase of the diversion project in Beizhao,Yuncheng city,and the basic situation of the diversion irrigation area in Beizhao.It analyzes the hydraulic calculation of the inverted siphon schemes building in the main canal after replacing the aqueducts,and determines the design scheme through the comprehensive comparison of construction conditions,operation management and project investment.
出处
《山西水利科技》
2020年第2期30-33,57,共5页
Shanxi Hydrotechnics
关键词
改扩建
水头损失
过流能力
非均匀流水面线计算
方案比选
reconstruction and expansion
head loss
overcurrent capacity
calculation of non-uniform flow surface line
comparison and selection of schemes