摘要
本文通过应力解除法在郭屯煤矿巷道中选取了4个测点,进行原岩应力测试,分析原岩应力分布规律以指导矿井更加安全高效的生产。结果显示:最大主应力为水平应力,方向为119.03°~122.01°;工作面巷道掘进方向与最大水平应力已接近垂直,水平应力对巷道围岩控制和底板破坏深度影响严重。
In this paper,through the stress relief method,four measuring points are selected in Guotun Coal Mine roadway to test the primary rock stress and analyze the stress distribution law of primary rock,so as to guide the safe and efficient production of the mine.The results show that:the maximum principal stress is horizontal stress,the direction is 119.03°to 122.01°;and the heading direction of working face is nearly vertical to the maximum horizontal stress,and the horizontal stress has a serious impact on the surrounding rock control and floor failure depth.
作者
赵艳鹏
牛海连
邵珠娟
Zhao Yan-peng;Niu Hai-lian;Shao Zhu-juan(Heze Coal Power Co.,Ltd.,Linyi Mining Group,Shandong Yuncheng 2740201;Jining Senior Vocational School,Shandong Jining 272001;Linyi Mining Group Co.,Ltd.,Shandong Linyi 276017)
出处
《山东煤炭科技》
2020年第8期155-157,165,共4页
Shandong Coal Science and Technology
关键词
原岩应力
郭屯煤矿
测试与分析
stress of primary rock
Guotun Coal Mine
testing and analysis