对隧洞开挖过程中超标准抽排水费用的计算,以抽水方量m^3计算,但部分项目无抽水方量计量资料,结合某水利工程抽水电量为计量单位计算抽水费用,执行现行的水利工程计价规定,解决了计量与计价的不配套,为同类项目抽水费用计算提供参考。
For cost calculation of super standard pumping and drainage in the process of tunnel excavation,the pumping volume is calculated in cubic meters,but some projects do not have pumping volume measurement data.This paper combines the pumping power of a water conservancy project as the measurement unit to calculate the pumping cost,which not only solves the mismatch between measurement and pricing,but also combines the current pricing regulations of water conservancy projects to calculate the pumping cost of similar projects Calculation provides reference.
作者
杨义忠
连新华
张琴凤
YANG Yizhong;LIAN Xinhua;ZHANG Qinfeng(China Water Resource Pearl River Planning Surveying & Designing Co., Ltd,Guangzhou 510610,China)
出处
《广东水利水电》
2020年第8期106-108,共3页