摘要
为了优化设计,采用三维有限元的方式对玉树国庆水库沥青混凝土心墙坝进行分析。基于各种配合比下沥青混凝土性能试验研究,通过对水库正常运行期工况进行模拟,研究推荐配合比下心墙参数对坝体以及心墙运行状态的影响。结果表明:防渗心墙尺寸设计合理,坝体及分区合适;推荐心墙配合比参数满足大坝运行条件;坝体和心墙间存在一定程度的“拱效应”。
In order to optimize the design,a three-dimensional finite element method is used to analyze the asphalt concrete core dam of the Guoqing Reservoir in Yushu,Qinghai.Based on the experimental research of asphalt concrete performance under various mix ratios,the influence of core wall parameters under recommended mix ratios on the operation of dam body and core wall is studied by simulating the working conditions of the reservoir during normal operation.The results show that the size of the impervious core wall is reasonable,and the dam body and zoning design are appropriate;the recommended mix ratio of core wall concrete meet the requirement of dam operating conditions;certain"arch effect"exists between the dam body and the core wall.
作者
闫飞
王波雷
刘锁
于春亮
YAN Fei;WANG Bolei;LIU Suo;YU Chunliang(PowerChina Northwest Engineering Corporation Limited, Xi'an 710065,China;Jinan Water Conservancy Design and Research Institute Co., Ltd., Jinan 250101,China)
出处
《西北水电》
2020年第4期98-101,共4页
Northwest Hydropower
关键词
沥青混凝土心墙
配合比试验
三维有限元
应力变形
asphalt concrete core wall
mix ratio test
three-dimensional finite element
stress and deformation