摘要 为了提高路基下沉整治工程中的成本管控,以D工务段L线路基下沉整治工程为依托,应用成本计划评审法对施工工期以及成本进行优化,结果表明:每单侧100 m(1项)路基下沉整治工程相比原始计划成本可节约8 490元,工期可缩短4 d,提高了工作效率,降低了养护维修成本. In order to improve the cost control of subgrade subsidence treatment project, based on the treatment project of L line foundation sinking in D Engineering Department, the PERT/Cost is used to optimize the construction period and cost. The results show that compared with the original plan, the cost of each side of 100 m(1 item) subgrade subsidence treatment project can be saved by 8490 yuan, and the construction period can be shortened by 4 days so as to improve the work efficiency and reduce the maintenance and repair costs.
作者 方文彬 张希望 FANG Wen-bin;ZHANG Xi-wang(Lanzhou University of Finance and Economics,Lanzhou 730020,China)
出处 《兰州工业学院学报》 2020年第4期52-56,共5页 Journal of Lanzhou Institute of Technology
关键词 成本计划评审法 路基下沉整治工程 成本管控 PERT/Cost subgrade sinking improvement project cost control
  • 相关文献

参考文献5

二级参考文献22

共引文献61

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部