期刊文献+

不等跨独塔双索面斜拉桥的施工控制及效果分析 被引量:1

Construction Control and Effect Analysis on Double Cable Planes Cable-stayed Bridge with Unequal Spans and Single Tower
原文传递
导出
摘要 不等跨独塔双索面斜拉桥的结构受力复杂,钢箱梁结构形式多具非静定特征,其施工控制具有较大难度。为保证桥梁的成桥状态符合设计要求,该文对其施工控制措施及控制效果进行了综合研究。实例分析表明:桥梁施工过程中的控制措施具有针对性,遵循动态监测、信息化施工的原则;同时,通过监测成果与计算结果的对比分析,得出主桥标高实测值与计算值之间的差值最大为6mm,轴线偏离位移最大值为9mm,主塔偏位误差最大为8.3mm,均满足精度控制要求。 The force of the structure of double cable planes cable-stayed bridge with unequal spans and single tower is complicated, and many structural forms of steel box girder has non-statically determinate characteristics, so its construction control is very difficult. In order to ensure that the completed state of the bridge meets the design requirements, this paper makes a comprehensive study on the construction control measures and control effect. The example analysis shows that the control measures in the process of bridge construction have pertinence, and follow the principles of dynamic monitoring and information construction. At the same time, through the comparative analysis of the monitoring results and calculation results, it concludes that the maximum difference between the measured and calculated values of the elevation of main bridge is 6 mm, the maximum value of axis deviation displacement is 9 mm, and the maximum deviation error of the main tower is 8.3 mm, which all meet the requirements of accuracy control.
作者 丁广炜 Ding Guangwei(Shaanxi Railway Institute)
出处 《勘察科学技术》 2020年第3期46-50,共5页 Site Investigation Science and Technology
基金 陕西铁路工程职业技术学院科研基金项目(编号KY2018-76)。
关键词 斜拉桥 钢箱梁 受力分析 施工控制 现场监测 cable-stayed bridge steel box girder force analysis construction control field monitoring
  • 相关文献

参考文献8

二级参考文献47

共引文献74

同被引文献1

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部