摘要
简要介绍了金地中心空调系统的设计,重点阐述了项目施工招投标阶段碰到的问题,并指出一些需要设计过程中提前考虑的因素,供以后类似项目的空调设计参考。
Briefly presents the HVAC system design of Jindi Center,focuses on problems encountered during construction tendering and bidding;Points out some construction site factor that need to be considered before the design,and provides reference for similar air conditioning designs.
作者
谢泽鑫
XIE Ze-xin(Zhubo Dedign Group Co.,Ltd.)
出处
《建筑热能通风空调》
2020年第6期103-105,共3页
Building Energy & Environment
关键词
超高层建筑
设计
招投标
对策
super high-rise building
design
tendering and bidding
solutions