摘要
本文中作者介绍了一起1000kV油浸式电抗器高压套管乙炔严重超标的缺陷,简要介绍了现场更换套管的关键工序,套管返厂解体后查明造成乙炔超标的原因,并提出了相应的建议。
The defect of 1000 kV oil-immersed reactor HV bushings acetylene seriously exceeding the standard is introduced by the authors in this paper.The key process of replacing the bushings on site is introduced.The cause of the excess acetylene is found out after plant dismantling,and the corresponding suggestions is proposed.