摘要
介绍了沙特阿美燃气增压站master gas system(MGS)二期项目管线等级及其无损探伤要求,对MGS项目无损探伤优缺点进行了分析,综合讨论了阿美MGS项目无损探伤管理,包含资质说明、程序提交、过程管理和阿美项目黄金焊缝。指出无损探伤工作的精细管理对于项目焊接技术质量评价、无损探伤组织管理、项目过程管理具有重要意义,进而为中国企业进入阿美管线项目的实施和程序上的误区避免提供参考和指导。
The pipeline grade and non-destructive testing requirements of Saudi Aramco gas booster station master gas system(MGS)second phase project are introduced,and the advantages and disadvantages of non-destructive testing of MGS project and comprehensively discusses the non-destructive testing management of Saudi Aramco MGS project are analyzed,including qualification description,procedure submission,process management and gold weld joint of Saudi Aramco project.It is pointed out that the fine management of non-destructive testing is of great significance to the quality evaluation of welding technology,the organization and management of non-destructive testing,and the process management of the project,so as to provide reference and guidance for Chinese enterprises to avoid mistakes in the implementation and procedures of entering the Aramco pipeline project.
作者
王纯
董占凯
李新洪
李宏宇
WANG Chun;DONG Zhankai;LI Xinhong;LI Hongyu(SEPCO Electric Power Construction Corporation,Jinan 250014,China)
出处
《焊管》
2020年第8期61-64,共4页
Welded Pipe and Tube
关键词
无损探伤
燃气增压站
沙特阿美
non-destructive testing
master gas system expansion
Saudi Aramco