摘要
2019年南方电网提出“数字南网”建设方案,将数字化作为发展战略之一,在试点项目中通过BIM技术在变电工程数字化建设的项目前期、工程前期、工程施工、工程总结的4个阶段,全过程支撑档案、质量、安全、进度、造价、验收等相关活动的管理咨询工作,切实满足电网数字化建设中的提质、增效的要求。
In 2019,China Southern Power Grid puts forward the"Digital South Grid"construction scheme,taking digitization as one of the development strategies.In the pilot project,BIM Technology was used to support the management and consultation work contents of archives,quality,safety,progress,cost,acceptance and other activities in the whole process through the four stages of digital construction of substation project,namely,the preliminary stage,the early stage,the construction stage and the summary stage of the project,so as to meet the requirements of improving quality and increasing efficiency in the digital construction of power grid.
作者
欧镜锋
李康华
曹文艳
田静
白珂
Ou Jingfeng;Li Kanghua;Cao Wenyan;Tian Jing;Bai Ke(Guangdong Chengyu Engineering Consultation and Supervision Co.,Ltd.,Foshan,528200,Guangdong;Guangzhou Joy-Youth Science&Technology Co.,Ltd.,Guangzhou,510030,Guangdong)
出处
《建设科技》
2020年第17期93-97,共5页
Construction Science and Technology
关键词
数字化建设
全过程咨询服务
数字孪生
风险前置管理
模库一体化
全过程电子化移交、全生命周期资产管理
digital construction
whole process consulting service
digital twin
pre-risk management
model library integration
whole process electronic transfer
life cycle asset management