本文通过一个采用复合土钉墙支护方案的基坑工程变形加固的典型案例,结合作者多年的设计施工经验,总结了一些基坑土钉墙支护变形控制、应急处置要点。
Through a typical case of deformation reinforcement of foundation pit engineering using composite soil nail wall support,this article summarizes some key points of deformation control and emergency treatment of foundation pit soil nail wall support by combining with the author's years of design and construction experience.
作者
黄望来
王咸东
侯国伟
HUANG Wang-lai;WANG Xian-dong;HOU Guo-wei(Kunming Junlong Geotechnical Engineering Co.,Ltd.,Kunming 650214,China)
出处
《价值工程》
2020年第28期126-128,共3页
Value Engineering
关键词
基坑
土钉墙支护
变形控制
应急处置
foundation pit
soil nail wall support
deformation control
emergency treatment