基于红岩煤矿按传统走向长壁采煤法时,区段巷道布置在煤层,留设区段煤柱,自上而下逐段回采,存在采空区水害和区段煤柱损失大等问题。研究出一种上行无煤柱走向长壁跨上山连续开采方法,既解决了工作面水害,回采率还提高了17%,沿空留巷顶底移近最大29 mm,两帮移近量最大19 mm。
Based on the traditional strike long wall mining method in Hongyan Coal Mine,the section roadways are arranged in the coal seam,the section coal pillars are reserved and the mining is carried out section by section from top to bottom.A continuous mining method with long wall and over hill in upward direction without coal pillar is studied.It not only solves the water disaster of working face,but also improves the recovery rate by 17%.The maximum displacement of the top and bottom of gob side entry retaining is 29 mm,and the maximum displacement of two sides is 19 mm.
作者
许多康
郭正文
Xu Duokang;Guo Zhengwen(Statistics Center of Chongqing Coal Regulatory Bureau,Chongqing 401121;Hongyan Coal Mine of Chongqing Energy Investment Co.,Ltd,Chongqing 400800)
出处
《山东煤炭科技》
2020年第9期100-102,107,共4页
Shandong Coal Science and Technology
关键词
上行
开采
沿空
采煤法
upward
mining
along gob area