摘要 为了解决干河煤矿右翼辅运巷轨10点前约28m处底鼓达1m的严重问题,通过现场调研与理论分析的方法确定该段底鼓为挤压流动性底鼓,并计算得到底板破坏深度为2.35m。并设计补打排距800mm、距底板200mm、与水平方向夹角为50°的底角穿煤岩接触面锚杆和切槽宽度500mm,深度2m的底板开槽方案的底鼓综合治理措施,措施应用后较未应用底鼓治理措施时1m的顶底板移近量下降80.5%,且未发生二次底鼓,底鼓综合治理效果显著。 In order to solve the serious problem that the bottom drum reaches 1m at about 28 meters before the 10th point of the right-wing auxiliary transportation lane rail of Ganhe Coal Mine,the bottom drum of this section is determined to be a squeezing fluid bottom drum through field investigation and theoretical analysis,and the floor is calculated.The destruction depth is 2.35m.And design the comprehensive treatment measures of the bottom drum with a row distance of 800mm,a distance of 200mm from the bottom plate,a bottom angle penetrating through the coal rock contact surface with a horizontal angle of 50°,and a slot width of 500mm and a depth of 2m.After the application of the measures,the approach distance of the 1m top and bottom plates decreased by 80.5%compared with when the bottom drum control measures were not applied,and no secondary bottom drum occurred,and the comprehensive treatment effect of the bottomdrumwas significant.
作者 李伟 LI Wei(Shanxi Hobao Ganhe Coal Mine Co.,Ltd.,Linfen 041602,China)
出处 《煤矿现代化》 2020年第6期80-82,85,共4页 Coal Mine Modernization
关键词 底板鼓起 破坏类型 底板开槽 底鼓治理 Floor swell Destruction type Slotted floor Kick drum governance
  • 相关文献

参考文献3

二级参考文献27

共引文献43

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部